The City of Lakewood Building Energy Benchmarking Ordinance is a citywide energy benchmarking & disclosure program requiring owners of existing buildings to report energy use annually, using ENERGY STAR® Portfolio Manager®. Effective as of February 2026, this program provides building owners insight into their building’s energy efficiency and helps meet the City of Lakewood’s Climate Action Plan goals.

BEGIN COMPLIANCE NOW

WHAT BUILDINGS ARE COVERED UNDER LAKEWOOD BENCHMARKING?

Property Size

Commercial, multifamily, and public buildings 10,000 Sq. Ft. or larger.

WHAT INFORMATION IS REQUIRED FOR BENCHMARKING?

Annual benchmarking reporting requires 12 calendar months of whole-building energy and building use data. For example, in 2025, building owners must report 12 months of 2024 data.

Note: Lakewood buildings that need to comply with the State’s Building Performance Colorado, can continue reporting according to the state’s schedule and simply add Lakewood as another reporting entity.

WHEN ARE LAKEWOOD BENCHMARKING REPORTS DUE?

December 31, 2026 and every June 1 thereafter. Benchmarking reports must be submitted on an annual basis using the previous year’s data via ENERGY STAR® Portfolio Manager®. This is the EPA’s benchmarking tool that is used for compliance reporting in most ordinances across the country.

WHAT INFORMATION IS REQUIRED FOR BPS?

Building Performance Standards (BPS) are often considered Phase II of these building energy use ordinances. After reporting your benchmarking data, many ordinances require you to make changes to the building’s operations or equipment to lower energy use over time.

Lakewood is currently developing its Building Performance Standards program and is expected in 2027.

WHEN ARE LAKEWOOD BPS REPORTS DUE?

BPS Due Date

Lakewood BPS is expected to be adopted in 2027.

WHAT IS THIRD-PARTY DATA VERIFICATION?

Third-party data verification requires owners/managers of covered buildings to hire a third-party expert who will independently review and verify the building’s benchmarking data.

Under Lakewood’s policy, data verification is not currently required. However, third-party data verification is often a key aspect of confirming compliance with building performance standards.

WHAT ARE THE PENALTIES IF YOU DON'T COMPLY WITH LAKEWOOD BENCHMARKING?

Failure to comply with Lakewood’s benchmarking policy can result in a fine up to $2,000. If a building owner fails to pay the fine, the City can place a lien on the property.

HOW DO I COMPLY WITH LAKEWOOD BENCHMARKING?

CONTACT US HERE to learn more and get started with compliance.

Lakewood Benchmarking compliance can be confusing and hard to navigate. Bringing on a consultant like VCA Green streamlines the entire process while ensuring accurate reporting. We also offer free consultations with our benchmarking clients to review the reports and identify inefficiencies to improve.

WHEN SHOULD I START LAKEWOOD BENCHMARKING COMPLIANCE?

Ordinances such as the Lakewood Energy Benchmarking Ordinance are already in effect across the country, and deadlines are rapidly approaching. Retrieving historical building data will take time, especially when coordinating with property managers and utilities.

Waiting until the last minute risks missing compliance windows resulting in fines and enforcement penalties. VCA Green takes every measure to ensure complete and accurate data collection. The sooner you reach out, the sooner you will reach compliance.

VCA GREEN PROCESS

With every phase of the process, VCA Green’s experienced and knowledgeable team is here to guide you on the results, options, and path forward to meet your compliance goals.

RELEVANT SERVICES

Fort Collins Building Energy and Water Scoring (BEWS) is a citywide energy benchmarking & disclosure program requiring owners of existing buildings to report energy and water use annually, using ENERGY STAR® Portfolio Manager®. Effective as of December 2018, this program provides building owners insight into their building’s energy efficiency and helps meet the City of Fort Collins’ Climate Action Plan goals.

BEGIN COMPLIANCE NOW

WHAT BUILDINGS ARE COVERED UNDER FORT COLLINS BEWS?

Property Size

Commercial buildings 5,000 Sq. Ft. or larger.

WHAT INFORMATION IS REQUIRED FOR BENCHMARKING?

Annual benchmarking reporting requires 12 calendar months of whole-building energy, water, and building use data. For example, in 2025, building owners must report 12 months of 2024 data.

WHEN ARE FORT COLLINS BEWS BENCHMARKING REPORTS DUE?

June 1, annually. Benchmarking reports must be submitted on an annual basis using the previous year’s data via ENERGY STAR® Portfolio Manager®. This is the EPA’s benchmarking tool that is used for compliance reporting in most ordinances across the country.

WHAT INFORMATION IS REQUIRED FOR BPS?

Building Performance Standards (BPS) are often considered Phase II of these building energy use ordinances. After reporting your benchmarking data, many ordinances require you to make changes to the building’s operations or equipment to lower energy use over time.

Fort Collins does not currently have a BPS program.

WHAT IS THIRD-PARTY DATA VERIFICATION?

Third-party data verification requires owners/managers of covered buildings to hire a third-party expert who will independently review and verify the building’s benchmarking data.

Under Fort Collins BEWS, data verification is not required to be completed by a third party. However, building owners must run their data through ENERGY STAR Portfolio Manager’s data quality checker.

WHAT ARE THE PENALTIES IF YOU DON'T COMPLY WITH FORT COLLINS BEWS?

Failure to comply with Fort Collins BEWS can result in a fine up to $3,000 per year of non-compliance.

HOW DO I COMPLY WITH FORT COLLINS BEWS?

CONTACT US HERE to learn more and get started with compliance.

Fort Collins Building Energy and Water Scoring (BEWS) compliance can be confusing and hard to navigate. Bringing on a consultant like VCA Green streamlines the entire process while ensuring accurate reporting. We also offer free consultations with our benchmarking clients to review the reports and identify inefficiencies to improve.

WHEN SHOULD I START FORT COLLINS BEWS COMPLIANCE?

Ordinances such as Fort Collins BEWS are already in effect across the country, and deadlines are rapidly approaching. Retrieving historical building data will take time, especially when coordinating with property managers and utilities.

Waiting until the last minute risks missing compliance windows resulting in fines and enforcement penalties. VCA Green takes every measure to ensure complete and accurate data collection. The sooner you reach out, the sooner you will reach compliance.

VCA GREEN PROCESS

With every phase of the process, VCA Green’s experienced and knowledgeable team is here to guide you on the results, options, and path forward to meet your compliance goals.

RELEVANT SERVICES

The City of Aspen Building IQ is a citywide energy benchmarking & disclosure program requiring owners of existing buildings to report energy and water use annually, using ENERGY STAR® Portfolio Manager®. Effective as of April 2022, this program provides building owners insight into their building’s energy efficiency and helps meet the City of Aspen’s Climate Action Plan goals.

BEGIN COMPLIANCE NOW

WHAT BUILDINGS ARE COVERED UNDER ASPEN BUILDING IQ?

Property Size

Commercial buildings 5,000 Sq. Ft. or larger.

Multifamily buildings 15,000 Sq. Ft. or larger.

WHAT INFORMATION IS REQUIRED FOR BENCHMARKING?

Annual benchmarking reporting requires 12 calendar months of whole-building energy, water, and building use data. For example, in 2025, building owners must report 12 months of 2024 data.

WHEN ARE ASPEN BUILDING IQ BENCHMARKING REPORTS DUE?

June 1, annually. Benchmarking reports must be submitted on an annual basis using the previous year’s data via ENERGY STAR® Portfolio Manager®. This is the EPA’s benchmarking tool that is used for compliance reporting in most ordinances across the country.

WHAT INFORMATION IS REQUIRED FOR BPS?

Building Performance Standards (BPS) are often considered Phase II of these building energy use ordinances. After reporting your benchmarking data, many ordinances require you to make changes to the building’s operations or equipment to lower energy use over time.

The Aspen Building IQ building performance standards policy is currently under development. The ordinance provides framework for the policy that it must contribute to reductions in community greenhouse gas emissions of 63% by 2030 and achieve net zero emissions by 2050.

WHEN ARE ASPEN BUILDING IQ BPS REPORTS DUE?

BPS Due Date

BPS policy and deadlines are still being developed.

WHAT IS THIRD-PARTY DATA VERIFICATION?

Third-party data verification requires owners/managers of covered buildings to hire a third-party expert who will independently review and verify the building’s benchmarking data.

Under Aspen Building IQ, data verification is not currently required. However, once the BPS policy is established, data verification is often included to confirm buildings have met their performance targets.

WHAT ARE THE PENALTIES IF YOU DON'T COMPLY WITH ASPEN BUILDING IQ?

Aspen Building IQ violations will result in a $100 fine for the first offense, $200 fine for the second offense, and potential mandatory court appearances and additional fines for subsequent offenses.

HOW DO I COMPLY WITH ASPEN BUILDING IQ?

CONTACT US HERE to learn more and get started with compliance.

Aspen Building IQ compliance can be confusing and hard to navigate. Bringing on a consultant like VCA Green streamlines the entire process while ensuring accurate reporting. We also offer free consultations with our benchmarking clients to review the reports and identify inefficiencies to improve.

WHEN SHOULD I START ASPEN BUILDING IQ COMPLIANCE?

Ordinances such as Aspen Building IQ are already in effect across the country, and deadlines are rapidly approaching. Retrieving historical building data will take time, especially when coordinating with property managers and utilities.

Waiting until the last minute risks missing compliance windows resulting in fines and enforcement penalties. VCA Green takes every measure to ensure complete and accurate data collection. The sooner you reach out, the sooner you will reach compliance.

ASPEN BUILDING IQ RESOURCES

Climate Policy

Aspen Climate Action

Bill Text

Chapter 8.60

Ordinance Homepage

Aspen Building IQ

VCA GREEN PROCESS

With every phase of the process, VCA Green’s experienced and knowledgeable team is here to guide you on the results, options, and path forward to meet your compliance goals.

RELEVANT SERVICES

The City of Boulder Building Performance Ordinance (BPO) is a citywide energy benchmarking & efficiency program requiring owners of existing buildings to report energy use annually, using ENERGY STAR® Portfolio Manager®. Effective as of October 2015, this program provides building owners insight into their building’s energy efficiency and helps meet the City of Boulder’s Climate Action Plan goals.

BEGIN COMPLIANCE NOW

WHAT BUILDINGS ARE COVERED UNDER BOULDER BPO?

Property Size

Privately owned commercial and industrial buildings that are 20,000 Sq. Ft. or larger.

City-owned buildings that are 5,000 Sq. Ft. or larger.

Newly built commercial and industrial buildings that are 10,000 Sq. Ft. or larger. New buildings are defined as buildings whose initial building permit was issued on or after January 31, 2014 under Boulder BPO.

WHAT IS REQUIRED FOR BOULDER BPO RATING AND REPORTING?

Rating and Reporting, also known as benchmarking, requires 12 calendar months of whole-building energy and building use data. For example, in 2025, building owners must report 12 months of 2024 data.

WHEN IS BOULDER BPO RATING AND REPORTING DUE?

June 1, annually. Rating and Reporting reports must be submitted on an annual basis using the previous year’s data via ENERGY STAR® Portfolio Manager®. This is the EPA’s benchmarking tool that is used for compliance reporting in most ordinances across the country.

WHAT IS REQUIRED FOR BOULDER BPO ENERGY ASSESSMENTS?

Boulder BPO requires affected buildings to complete energy assessments every ten years. Affected buildings that are less than 50,000 Sq. Ft. must complete ASHRAE Level I assessments and affected buildings that are 50,000 Sq. Ft. or larger must complete ASHRAE Level II assessments.

All assessments must be completed by a Qualified Service Provider.

WHEN ARE BOULDER BPO ENERGY ASSESSMENTS DUE?

Energy assessments are required every ten years and following the timeline below:

  • City buildings 10,000 Sq. Ft. or larger – May 1, 2019
  • Existing buildings 50,000 Sq. Ft. or larger – June 1, 2019
  • New buildings 10,000 Sq. Ft. or larger – June 1, 2019
  • Existing buildings 30,000 Sq. Ft. or larger but less than 50,000 Sq. Ft. – December 31, 2021
  • Existing buildings 20,000 Sq. Ft. or larger but less than 30,000 Sq. Ft. – June 1, 2023

WHAT IS REQUIRED FOR BOULDER BPO LIGHTING UPGRADES?

Boulder BPO requires affected buildings to complete a one-time lighting upgrade. These upgrades must reach compliance with the City of Boulder Energy Conservation Codes (COBECC) according to the list below:

  • Occupancy Sensor Controls must meet the 2017 COBECC section C405.2.2.2
  • Time-switch Controls must meet the 2017 COBECC section C405.2.2.1
  • Exterior Lighting Controls must meet the 2017 COBECC section C405.2.4
  • Interior Lighting – Power must meet 2017 COBECC section C405.5
  • Exterior Lighting – Power must meet 2012 International Energy Conservation Code (IECC) section C405.6

WHEN ARE BOULDER BPO LIGHTING UPGRADES DUE?

One-time lighting upgrades were due according to the following timeline:

  • City buildings 10,000 Sq. Ft. or larger – May 1, 2022
  • Existing buildings 50,000 Sq. Ft. or larger – June 1, 2022
  • New buildings 10,000 Sq. Ft. or larger – June 1, 2022
  • Existing buildings 30,000 Sq. Ft. or larger but less than 50,000 Sq. Ft. – June 1, 2023
  • Existing buildings 20,000 Sq. Ft. or larger but less than 30,000 Sq. Ft. – June 1, 2025

WHAT IS REQUIRED FOR BOULDER BPO RETRO-COMMISSIONING?

Boulder BPO requires affected buildings to conduct retro-commissioning (RCx) studies and implement all measures with a payback period of two years or less. RCx studies must be completed by a qualified service provider.

WHEN IS BOULDER BPO RETRO-COMMISSIONING DUE?

Retro-commissioning studies must be completed according to the timeline below. All RCx measures must be implemented within two years of the study.

  • City buildings 10,000 Sq. Ft. or larger – May 1, 2022
  • Existing buildings 50,000 Sq. Ft. or larger – June 1, 2022
  • New buildings 10,000 Sq. Ft. or larger – June 1, 2022
  • Existing buildings 30,000 Sq. Ft. or larger but less than 50,000 Sq. Ft. – June 1, 2023
  • Existing buildings 20,000 Sq. Ft. or larger but less than 30,000 Sq. Ft. – June 1, 2025

WHAT ARE THE PENALTIES IF YOU DON'T COMPLY WITH BOULDER BPO?

Boulder Building Performance Ordinance requires affected buildings to rate and report building energy data and complete efficiency actions by their respective deadlines.

Failure to meet a deadline can result in fines of $0.0025 per Sq. Ft. up to $1,000 per day of non-compliance.

HOW DO I COMPLY WITH BOULDER BPO?

CONTACT US HERE to learn more and get started with compliance.

Boulder Building Performance Ordinance compliance can be confusing and hard to navigate. Bringing on a consultant like VCA Green streamlines the entire process while ensuring accurate reporting. We also offer free consultations with our benchmarking clients to review the reports and identify inefficiencies to improve.

WHEN SHOULD I START BOULDER BPO COMPLIANCE?

Ordinances such as Boulder BPO are already in effect across the country, and deadlines are rapidly approaching. Retrieving historical building data will take time, especially when coordinating with property managers and utilities.

Waiting until the last minute risks missing compliance windows resulting in fines and enforcement penalties. VCA Green takes every measure to ensure complete and accurate data collection. The sooner you reach out, the sooner you will reach compliance.

BOULDER BPO RESOURCES

VCA GREEN IS A BOULDER BPO AUTHORIZED SERVICE PROVIDER

VCA GREEN PROCESS

With every phase of the process, VCA Green’s experienced and knowledgeable team is here to guide you on the results, options, and path forward to meet your compliance goals.

RELEVANT SERVICES

Building Performance Colorado is a statewide energy benchmarking & disclosure program requiring owners of existing buildings to report energy use annually, using ENERGY STAR® Portfolio Manager®. Effective as of October 2023, this program provides building owners insight into their building’s energy efficiency and helps meet the State of Colorado’s Climate Action Plan goals.

BEGIN COMPLIANCE NOW

WHAT BUILDINGS ARE COVERED UNDER BUILDING PERFORMANCE COLORADO?

Property Size

All existing buildings 50,000 Sq. Ft. and above.

WHAT INFORMATION IS REQUIRED FOR BENCHMARKING?

Annual benchmarking reporting requires 12 calendar months of whole-building energy and building use data. For example, in 2026, building owners must report 12 months of 2025 data.

WHEN ARE BUILDING PERFORMANCE COLORADO BENCHMARKING REPORTS DUE?

November 1, annually. Benchmarking reports must be submitted on an annual basis using the previous year’s data via ENERGY STAR® Portfolio Manager®. This is the EPA’s benchmarking tool that is used for compliance reporting in most ordinances across the country.

WHAT INFORMATION IS REQUIRED FOR BPS?

Building Performance Standards (BPS) are often considered Phase II of these building energy use ordinances. After reporting your benchmarking data, many ordinances require you to make changes to the building’s operations or equipment to lower energy use over time.

Building Performance Colorado requires covered properties to meet BPS targets in 2026 and 2030. These targets can be achieved by completing one of the following compliance pathways:

  • Meet the site energy use intensity (EUI) targets set based on the building’s use type
  • Meet the greenhouse gas intensity (GHGI) targets set based on the building’s use type
  • Achieve a site EUI reduction of 13% in 2026 and 29% in 2030 from its 2021 baseline EUI data
  • Achieve a GHGI reduction of 13% in 2026 and 29% in 2030 from its 2021 baseline GHG emissions data

Buildings owners were required to select their pathway by July 1, 2025. Pathway adjustment requests can be submitted up to December 31, 2026.

WHEN ARE BUILDING PERFORMANCE COLORADO BPS REPORTS DUE?

BPS Due Date

Covered buildings must achieve their building type’s target or emissions reduction percentage by 2026 and 2030. Building owners will demonstrate 2026 compliance through their benchmarking report due June 1, 2027, which reports the building’s energy use from January 1, 2026 to December 31, 2026.

WHAT IS THIRD-PARTY DATA VERIFICATION?

Third-party data verification requires owners/managers of covered buildings to hire a certified third-party expert who will independently review and verify the building’s benchmarking data.

Under Building Performance Colorado, data verification is required for every year of previous benchmarking data when the building requests a compliance pathway adjustment.

WHAT ARE THE PENALTIES IF YOU DON'T COMPLY WITH BUILDING PERFORMANCE COLORADO?

Violations of Building Performance Colorado’s benchmarking requirements will result in a $500 fine plus $2,000 per subsequent violation.

Failure to comply with Colorado’s BPS program will result in a $2,000 fine, plus $5,000 per subsequent violation.

HOW DO I COMPLY WITH BUILDING PERFORMANCE COLORADO?

CONTACT US HERE to learn more and get started with compliance.

We recognize that Building Performance Colorado compliance can be confusing and hard to navigate. Bringing on a consultant like VCA Green streamlines the entire process while ensuring accurate reporting. We also offer free consultations with our benchmarking clients to review the reports and identify inefficiencies to improve.

WHEN SHOULD I START BUILDING PERFORMANCE COLORADO COMPLIANCE?

Ordinances such as Building Performance Colorado are already in effect across the country, and deadlines are rapidly approaching. Retrieving historical building data will take time, especially when coordinating with property managers and utilities.

Waiting until the last minute risks missing compliance windows resulting in fines and enforcement penalties. VCA Green takes every measure to ensure complete and accurate data collection. The sooner you reach out, the sooner you will reach compliance.

BUILDING PERFORMANCE COLORADO RESOURCES

VCA GREEN PROCESS

With every phase of the process, VCA Green’s experienced and knowledgeable team is here to guide you on the results, options, and path forward to meet your compliance goals.

RELEVANT SERVICES

The City of Denver Building Performance Policy (Energize Denver), is a citywide energy benchmarking & disclosure program requiring owners of existing buildings to report energy use annually, using ENERGY STAR® Portfolio Manager®. Effective as of 2017, this program provides building owners insight into their building’s energy efficiency and helps meet the City of Denver’s Climate Action Plan goals.

BEGIN COMPLIANCE NOW

WHAT BUILDINGS ARE COVERED UNDER ENERGIZE DENVER?

Property Size

Buildings between 5,000 and 24,999 Sq. Ft.

Buildings over 25,000 Sq. Ft.

WHAT INFORMATION IS REQUIRED FOR BENCHMARKING?

Annual benchmarking reporting requires 12 calendar months of whole-building energy and building use data. For example, in 2025, building owners must report 12 months of 2024 data.

WHEN ARE ENERGIZE DENVER BENCHMARKING REPORTS DUE?

June 1, annually. Benchmarking reports must be submitted on an annual basis using the previous year’s data via ENERGY STAR® Portfolio Manager®. This is the EPA’s benchmarking tool that is used for compliance reporting in most ordinances across the country.

WHAT INFORMATION IS REQUIRED FOR BPS?

Building Performance Standards (BPS) are often considered Phase II of these building energy use ordinances. After reporting your benchmarking data, many ordinances require you to make changes to the building’s operations or equipment to lower energy use over time.

Energize Denver requires covered properties over 25,000 Sq. Ft. to meet performance targets designated based on the building type.

Note: Denver implemented a maximum reduction limit such that none of these large covered buildings will have to reduce their Site EUI by 42% or more.

Buildings between 5,000 and 24,999 Sq. Ft. are required to either:

  • Improve Lighting: Certify that a minimum of 90% of the building’s total lighting load is provided by LED lights, or that all lighting meets 2019 Denver Building and Fire Code for lighting power density.
  • Improve Energy Source: Utilize on- or off-site renewable power generation to meet a minimum of 20% of the building’s annual site energy usage.

WHEN ARE ENERGIZE DENVER BPS REPORTS DUE?

BPS Due Date (25,000+ Sq. Ft.)

The specified Energy Use Intensity (EUI) target must be met by the buildings covered under that use type in 2027 and 2030. With an approval of a timeline extension, the deadlines are 2028 and 2032.

Performance Requirement Due Date (5,000-24,999 Sq. Ft.)

December 31, 2026 – Buildings 20,000 to 24,999 Sq. Ft.

December 31, 2027 – Buildings 15,000 to 19,999 Sq. Ft.

December 31, 2028 – Buildings between 10,000 and 14,999 Sq. Ft.

December 31, 2029 – Buildings between 5,000 and 9,999 Sq. Ft.

WHAT IS THIRD-PARTY DATA VERIFICATION?

Third-party data verification requires owners/managers of covered buildings to hire a third-party expert who will independently review and verify the building’s benchmarking data.

Under Energize Denver, data verification is required twice:

  • Initial benchmarking data must be verified by June 1, 2026 to confirm correct building information and use type
  • Final verification must be done to confirm the building meets the efficiency target in the final target year.

WHAT ARE THE PENALTIES IF YOU DON'T COMPLY WITH ENERGIZE DENVER?

Benchmarking reports not approved by September 1, 2025 are subject to a $2,000 fine. Denver also assesses performance penalties for non-compliance based on the amount of energy savings (in kBtu) not achieved:

$0.15/kBtu not achieved:

  • Buildings that do not opt into the updated compliance timeline
  • Buildings that fall out of compliance after meeting interim or final targets
  • Newly constructed buildings

$0.23/kBtu not achieved:

  • Buildings that are following the standard updated timeline with an interim target in 2028 and a final target in 2032

$0.35/kBtu not achieved:

  • Buildings that got a timeline extension and only have one target year for which Denver is assessing the data

$0.10/kBtu added to the penalty rate:

  • Buildings that request a timeline extension after December 31 of the target due date they are requesting an extension for

$10.00/square foot listed by the Office of the Assessor:

  • Buildings that have never submitted a benchmarking report
  • Buildings for whom the most recent benchmarking report is from before 2019

HOW DO I COMPLY WITH ENERGIZE DENVER?

CONTACT US HERE to learn more and get started with compliance.

Energize Denver compliance can be confusing and hard to navigate. Bringing on a consultant like VCA Green streamlines the entire process while ensuring accurate reporting. We also offer free consultations with our benchmarking clients to review the reports and identify inefficiencies to improve.

WHEN SHOULD I START ENERGIZE DENVER COMPLIANCE?

Ordinances such as Energize Denver are already in effect across the country, and deadlines are rapidly approaching. Retrieving historical building data will take time, especially when coordinating with property managers and utilities.

Waiting until the last minute risks missing compliance windows resulting in fines and enforcement penalties. VCA Green takes every measure to ensure complete and accurate data collection. The sooner you reach out, the sooner you will reach compliance.

ENERGIZE DENVER RESOURCES

VCA GREEN IS AN ENERGIZE DENVER AUTHORIZED SERVICE PROVIDER

VCA GREEN PROCESS

With every phase of the process, VCA Green’s experienced and knowledgeable team is here to guide you on the results, options, and path forward to meet your compliance goals.

RELEVANT SERVICES